Hello everyone! We have an update!
After having our septic permit in for nearly a year and having to jump through countless hoops, we have finally received approval to move forward on that part of our project. After discussing with our septic person, it looks like that should be installed at some point this winter.
We are working with our contractor on new building plans, as our original set was denied by the county, and we should have a timeline on that pretty soon.
At this point, it is our tentative plan to be open for business in May 2026, barring any more major issues.